PureOps completes first turnkey production well (300-gallon), with all the bells and whistles — and the well building to boot — serving the needs of Picacho MDWCA.
Supply and Installation of Equipment
- Clamp-on ultrasonic flow meter
- Polyphosphate injection system
- Chlorine gas injection system, including chlorine scales, automatic shut off actuators, gas detection equipment, injection booster pump, and chlorine residual analyzer
- Motor controls and all related electrical and SCADA equipment
Construction of 24’ x 13’ Well House
- Cement pad and foundation
- Tie-in newly drilled well to the distribution system
- Installation of 6” pump control and diaphragm check valves
- Discharge basin and pond area
- Construction of gravel access road